Construction progress continued on exterior walls and windows, piping and electrical inside the office section, switchgear and transformers in the electrical yard, and piping in the chiller section on the Terascale Simulation Facility during April 2003.

Click on a thumbnail for a larger image.

previous home next
Privacy & Legal Notice
Transformers are unloaded and set on concrete pads in the electrical yard
Transformers are unloaded and set on concrete pads in the electrical yard.


Installation of the exterior block siding.


The aluminum frame for the glass curtain wall is installed on the entrance to the office section.


Installing rebar and forms for the basins of the cooling towers.

View across the electrical yard of the installation of exterior panels on the west end of the computer room.

Piping being installed in the chiller room.

Exterior panels and windows are installed on the south side of the third floor office section.

Another view of the basins for the cooling towers.

One of four large 1,200 ton chillers is delivered.

One of the 1,200 ton chillers is unloaded.

Preparing to pour concrete on the sloped floor in the large conference room.

The glass curtain wall is installed on the entrance to the office section.