Work on the Terascale Simulation Facility during the month of January 2003 included pouring concrete floors in the computer section and sealing the roof and installing edging, gutters, and downspouts. Work on the electrical yard continued, and installation of exterior siding began.

Click on a thumbnail for a larger image.

previous home next
Privacy & Legal Notice
Roofing is installed on the chiller section
Roofing is installed on the chiller section.

Air conditioning ductwork in the first computer room
Air conditioning ductwork in the first computer room.

Rain gutters and drains are installed on the south side of the first computer room
Rain gutters and drains are installed on the south side of the first computer room.

Fireproofing is applied to the steel on the third floor office section
Fireproofing is applied to the steel on the third floor office section.
Forms and rebar for a concrete pad for air-conditioning equipment on the roof of the office section
Forms and rebar for a concrete pad for air-conditioning equipment on the roof of the office section.
Electrical conduits are installed under the mechanical room slab floor
Electrical conduits are installed under the mechanical room slab floor.
Forms for the outside curb of the mechanical room slab floor
Forms for the outside curb of the mechanical room slab floor.
Fire sprinkler pipe is installed on the second floor office section
Fire sprinkler pipe is installed on the second floor office section.
A concrete pad for air handlers on the roof of the office section
A concrete pad for air handlers on the roof of the office section.
A worker finishes concrete that will provide temporary support for stairs on the ground floor
A worker finishes concrete that will provide temporary support for stairs on the ground floor.
Rebar is installed in the floor of the chiller room. Blue floor drain runs through the middle of the room
Rebar is installed in the floor of the chiller room. Blue floor drain runs through the middle of the room.
Forms for concrete are installed in the mechanical room under the computer room
Forms for concrete are installed in the mechanical room under the computer room.
A view of the office section; sand is poured on the ground floor in preparation for concrete
A view of the office section; sand is poured on the ground floor in preparation for concrete.
Rebar in the west mechanical room floor
Rebar in the west mechanical room floor floor, in preparation for concrete.
Finishing concrete on the chiller room floor
Finishing concrete on the chiller room floor.
Interior walls go up in the second floor office section
Interior walls go up in the second floor office section.
Edging is installed on the roof of the office section
Edging is installed on the roof of the office section.
Placing the large underground concrete vaults for the electrical substations
Placing the large underground concrete vaults for the electrical substations.
Steel studs for backing the exterior wall of the computer section
Steel studs for backing the exterior wall of the computer section.
Completion of the installation of the metal decking on the exterior of the large conference room
Completion of the installation of the metal decking on the exterior of the large conference room.